Organization & Preparation
Date
|
Task Description |
Done By |
01-02-2005 |
Visit to Van's Aircraft to see the RV-7 as an option to build it. After
landing from the test flight with the RV-7 I saw the RV-9A in the hangar
and at that very moment I
decided that this is the ONE.
|
Tal
|
01-05-2005 |
Ordered the Empennage and Wing kits
|
Tal |
18-07-2005 |
The Empennage and Wing kits arrived. Box 4 has an outside minor damage. (
the parts inside are O.K)
Packing List
|
|
01-01-2005 |
Moved to a house with a large yard and the most important a big
warehouse with a excellent potential to become a nice workshop.
|
Tal |
01-01-2005
To
01-12-2005 |
Converting the
warehouse into a
workshop.
1 - Electricity work, More lights, more outlets.
2 - Covering the inside walls and
ceiling with
plaster plates and thermal/acoustic
isolation plates between them and the
outside walls.
3 - Ordering and installing all the inside
furniture
needed for a workshop. (tables, shelf
etcetera)
4 - Ordering and installing all standard machinery (drilling machine,
clamp, strip saw, compressor etcetera)
|
Yossi
Tal
Orlev
Ronen |
01-12-2005
To
06-12-2005 |
1 - Unpacking and recognizing the special tools kit.
2 - Unpacking and recognizing the Empennage and Wing kit parts.
Cleaveland Tools
|
Yossi
Tal
Orlev |
06-12-2005
Midnight |
OK READY TO START THE BIG ADVENTURE ! ! !
Our goal is to See You in Dec - 2008
With a brand new ready to fly
RV-9A 4X-OTS
|
|
01-12-2006
To
05-12-2006 |
One year after the project began the shop is too small Mr Ronen and
his team came again ....
(Click here to view more pictures)
|
|
18-07-2007
To
20-07-2007 |
After a
couple off weeks of 30 - 40 C with
60 - 80 % humidity which started to
slow down the work we
decided to
air-condition the work shop
Mr Ronen and his team
came again..... |
|
Empennage
Horizontal Stabilizer
Date
|
Task Description |
Done By |
Hours |
07-12-2005 |
Assembling the skeleton of the horizontal stabilizer
|
Yossi
Tal |
6 |
09-02-2005 |
Assembling the left horizontal stabilizer skeleton into the skin.
|
Yossi
Orlev |
5 |
13-12-2005 |
1 - Assembling the right horizontal stabilizer skeleton into the skin.
2 - Match drill the skin to the skeletal structure. (Left and right)
3 - Disassemble the left and right horizontal stabilizers and deburr all
holes and edges.
|
Yossi
Tal
|
7 |
16-12-2005
to
18-12-2005 |
1 - Dimple the #40 holes in all rib flanges and skins for left and right
horizontal stabilizer. (the holes in the main ribs that go under the
front spar are left un dimpled)
2 - Countersink the #40 holes in all spar flanges and doublers.
|
Yossi
Tal
Orlev |
8 |
18-12-2005
to
19-12-2005 |
Prime all horizontal stabilizer with:
1 - Primary coat. EPOXZEN MIL-P 53022B1 2 component.
2 - Wash Primer. MIL-C-8514 2 component.
|
Tal |
5 |
20-12-2005
to
24-12-2005 |
Assembling the horizontal stabilizer.
|
Yossi
Tal
Orlev |
18.5 |
07-12-2005
to
24-12-2005 |
Total time |
Yossi
Tal
Orlev |
49.5 |
Congratulation !!!!!!
We finished the Horizontal Stabilizer
|
|
Vertical Stabilizer
Date
|
Task Description |
Done By |
Hours |
20-12-2005 |
1 - Assembling and Drilling the Vertical stabilizer,
2 - Marking disassembling and de-burring all parts.
|
Yossi
|
5 |
21-12-2005
to
26-12-2005 |
1 - Dimple and machine countersink parts as desired.
2 - Prime all parts.
|
Tal |
6 |
27-12-2005
to
28-12-2005 |
Finishing the Vertical stabilizer.
|
Yossi
Tal
Orlev |
2 |
20-12-2005
to
28-12-2005 |
Total time |
Yossi
Tal
Orlev |
13 |
Congratulation !!!!!!
We finished the Vertical Stabilizer
|
|
Rudder
Date
|
Task Description |
Done By |
Hours |
28-12-2005 |
1 - Fitting the stiffeners to the rudder skin. (riveting the stiffeners
to the skin will be done after priming all the parts of the rudder)
2 - Building the Rudder skeleton.
|
Yossi
Orlev |
9 |
29-12-2005 |
1 - Match drilling the Rudder
|
Yossi
Orlev |
4 |
30-12-2005 |
1 - deburr all holes and edges.
2 - dimple and countersink all parts.
|
Yossi
Tal
Orlev |
5 |
30-12-2005
to
31-12-2005 |
Priming the Rudder in 2 steps, First prime wash and after curing
priming.
|
Tal |
3.5 |
01-01-2006 |
1 - Riveting the stiffeners to the skin.
2 - Riveting the Rudder skeleton
|
Yossi
Tal
Orlev |
2.5 |
05-01-2006 |
1 - Riveting the skins to the skeleton.
2 - Preparing the trailing edge for riveting. we used Epoxy 3M -460 and
an 3mm aluminum angle drilled and clecoed to the trailing edge. (see
pic.)
|
Yossi
Tal |
2 |
10-01-2006 |
1 - Riveting the trailing edge. we followed the instruction except that
we insert the rivet flash head from both side
symmetrical. The results are perfect, the trailing edge is
straight
and the look of the rivets is nice and symmetric.
2 - Completing the leading edge.
|
Yossi
Tal |
1.5 |
28-12-2005
to
10-01-2006 |
Total time |
Yossi
Tal
Orlev |
27.5 |
Congratulation !!!!!!
We finished the Rudder
|
|
Elevators
Date
|
Task Description |
Done By |
Hours |
06-01-2006 |
changing the order of work from the instruction.
From the experience we got till
now we found that the prim overhead time is very significant. from that
reason
we decided to
accumulate maximum parts for priming. as a result we are changing
the order of work from the instruction.
1 - Fitting the stiffeners to the R/L elevators skin.
(riveting the stiffeners to the skin will be done after priming
all the parts) 2 - Building the elevators skeleton. 3 - Match
drilling all parts.
On E903 & E904 Tip ribs & E913
counterbalance skin we had to enlarge the #40 holes to #30 to overcome
the hole mismatch. this was only on the left Elevator but for esthetical
look we made the same on the right Elevator
|
Yossi
Tal
Orlev |
5 |
07-01-2006
to
14-01-2006 |
1 - Deburr dimple and prepare all elevators parts for prime. (Right &
Left)
|
Tal
Yair |
21.5 |
20-01-2006 |
1 - Prime all parts. (Right & Left)
|
Tal |
4.5 |
21-01-2006
to
04-02-2006 |
1 - Rivet all parts. (Right & Left)
changing the order of work from the
instruction.
In the right elevator we followed the instruction and rivet the
E-903/904/913 assembly to the E-902 spar that was already riveted to the
top skin, as a results we had an hard time riveting the AN470AD4-4. In
the left elevator we changed the order and rivet the E-903/904/913
assembly to the E-902 spar before riveting the spar to the top skin.
|
Tal
Yossi
Orlev |
27.5 |
06-01-2006
to
04-02-2006 |
Total time |
Yossi
Tal
Orlev |
58.5 |
Congratulation !!!!!!
We finished the Elevators
|
|
Finishing
Date
|
Task Description |
Done By |
Hours |
04-09-2007
to
06-09-2007 |
Fitting the
empennage fiberglass tips
|
Tal |
7.5 |
09-09-2007 |
Installing the elevator fiberglass tips with Pop rivets + 3M 460 Epoxy
glue
|
Tal |
3.5 |
15-09-2007 |
Installing the
rudder fiberglass tip with Pop rivets + 3M 460 Epoxy glue
|
Tal |
2 |
16-09-2007 |
Working on the elevator and rudder stabilizers tips
Fabricate VOR antenna bracket
|
Tal
Yossi
Orlev |
7.5 |
21-09-2007 |
Empennage tips …..
L
|
Tal
|
6 |
21-09-2007 |
Fabricate VOR antenna bracket
|
Yossi |
6 |
23-09-2007 |
Empennage tips …..
L
almost done ….
|
Tal
|
6.5 |
27-09-2007 |
Empennage tips …..
L
almost done ….
|
Tal
|
7.5 |
02-10-2007 |
Empennage tips are done ….
J
|
Tal
|
4 |
05-10-2007 |
Fabricating VOR Ant. bracket
|
Yossi |
3 |
20-10-2007 |
Empennage fairing
|
Tal
|
4 |
29-12-2008 |
Working on
the housing for the outside view camera on the VS top
fairing.
Cutting out the top fairing and gluing the camera housing into the
fairing.
|
Tal
|
4 |
24-01-2009 |
Filling the gap between the
camera housing and the firing.
|
Tal
|
4 |
04-09-2007
to
24-01-2009 |
Total time till now |
Yossi
Tal
Orlev |
65.5 |
Congratulation !!!!!! |
|
WINGS
Skeleton
Date
|
Task Description |
Done By |
Hours |
07-02-2006 |
preparing the workshop for the wing job.
1 - We decided to build a fixed (floor to ceiling) double wing working
stand with the main spar located at the shoulder height. the stand will
be made from wood.
2 - The finished wing cradle will be finished later using the wood from
the wing stand. 3 - for the tank and leading edge stands we made 4
individual stands (2 for each wing) so it will be used also to assist
while working on the fuel tanks.
|
Yossi
Tal |
8 |
10-02-2006 |
1 - Prepare the main spars. Machine countersink all platenuts
holes,
local prime the countersink area.
2 - Rivet all platenuts .
|
Yossi
Tal
Orlev |
6 |
15-02-2006 |
1 - Prepare the rear spars. drill all reinforcement forks and doublers
plate Machine countersink the necessary holes in the W-970C. deburr and
prepare all components for priming.
2 - Start to prepare the ribs. straighten
up and deburring.
|
Yossi
Tal |
9 |
17-02-2006 |
1 - Deburring ribs.
2 - Assemble the spars (main & rear) on the jig.
|
Yossi
Orlev |
3 |
20-02-2006
to
21-02-2006 |
1 - match drill ribs to spar (R & L)
2 - Align the skeleton on jig.
|
Tal
Tomer |
3 |
22-02-2006 |
1 - improvement on the jig to be abel to assemble the last outbord rib.
2 - Final improvement on the support at the
skeleton center.
|
Tal
|
1.5 |
23-02-2006 |
1 - more improvement on the jig.
2 - Cleco skins W902,W903 on (R & L).
|
Tal |
2.5 |
24-02-2006
to
25-02-2006 |
1 - final improvement on the jig and adjustments.
2 - Match drilling skins W902,W903 and J-stiffener W926A,B.
3 - Match drilling skins W904,W905.
|
Tal
Orlev |
11 |
03-03-2006
to
10-03-2006 |
Finish match drilling skins.
|
Yossi
Orlev
|
4.5 |
14-03-2006
|
1 - Preparing jigs for wing leading edge.
2 - Assemble (cleco) ribs into left leading edge skin.
|
Yossi
Orlev |
6 |
17-03-2006 |
1 - Assemble (cleco) ribs into right leading edge skin.
2 - Assemble and drilling W-908 L & R with w-918 joint plate.
3 - Modifying the outboard spar attachment to the jig to allow the
assembly of the leading edge later.
|
Yossi
Orlev |
7 |
18-03-2006 |
Match drilling leading edge skin (R & L).
|
Tal |
1.5 |
07-02-2006
to
18-03-2006 |
Total time |
Yossi
Tal
Orlev |
63 |
Congratulation !!!!!!
We finished the
wings skeleton
|
|
Fuel Tanks
Date
|
Task Description |
Done By |
Hours |
21-03-2006 |
Assemble (cleco) right fuel tank.
|
Tal |
2 |
22-03-2006 |
preparing T-911 fuel tank stiffeners.
|
Tal |
1.5 |
23-03-2006 |
preparing T-912 fuel tank attach brackets.
|
Tal |
1.5 |
24-03-2006 |
match drill right fuel tank to the wing. |
Yossi
Tal
Orlev |
3 |
26-03-2006 |
Fabricate T-905, fitting T-910 reinforcement plates in both sides,
drilling the platenuts to T-912 brackets
|
Tal |
2.5 |
28-03-2006 |
preparing Fuel cap, Drain flange cover plates T-406,T407,T-408 and VA112
|
Tal |
9 |
31-03-2006 |
1 - Preparing the capacitive gouge sender.
2 - Dimple deburr all ribs and skin.
3 - Prime all outer parts.
|
Tal
Yossi
Orlev |
7 |
01-04-2006 |
1 - Assemble platenuts to T-912.
2 - Fabricate T-905 for left fuel tank.
|
Tal |
2.5 |
13-04-2006 |
1 - Assemble (cleco) left fuel tank.
2 - preparing T-912 fuel tank attach brackets.
|
Tal |
2 |
14-04-2006 |
1 - Rivet with sealant right fuel tank stiffeners, Fuel cap, Drain
flange cover and ribs to the skin.
2 - Match drill left T-912 to main spar.
|
Tal
Yossi
Orlev |
9.5 |
19-04-2006
to
21-04-2006 |
1 - Assemble the capacitive gouge sender and the vent line on right fuel
tank.
2 - preparing T-912 fuel tank attach brackets and match drill left fuel
tank to the wing.
|
Tal
Yossi
Orlev |
6.5 |
05-05-2006 |
Final preparations before sealing the left fuel tank.
|
Yossi
Orlev |
3.0 |
12-05-2006 |
Rivet with sealant left fuel tank stiffeners, Fuel cap, Drain flange
cover and ribs to the skin.
|
Tal
Yossi
Orlev |
5.0 |
16-05-2006 |
Rivet with sealant left fuel tank ribs to the skin.
|
Tal
Oved |
2.0 |
19-05-2006 |
Rivet with sealant left fuel tank ribs to the skin.
|
Tal
Yossi
Orlev |
5.0 |
20-05-2006 |
Fabricate the T-915 anti rotation bracket.
|
Tal
Oved |
1 |
26-05-2006 |
Final assembly and wiring for the capacitive fuel senders
|
Tal
Yossi
Orlev |
3.0 |
27-05-2006 |
Sealing both fuel tank capacitive senders
|
Tal
Oved |
1 |
02-06-2006 |
1 - Final checks cleaning and preparations before sealing left T-902
tank baffle.
2 - Sealing and assembly left T-902 and T-912.
|
Tal
Yossi
Orlev |
6.0 |
03-06-2006 |
1 - Final checks cleaning and preparations before sealing right T-902
tank baffle.
|
Tal |
1.5 |
09-06-2006 |
1 - Sealing and assembly T-902 and T-912.
2 - Leak check for the left fuel tank ... :-( small leak was identified
between the corner of T-902 baffle and the outer end rib.
|
Tal
Yossi
Orlev |
4.0 |
15-06-2006 |
Leak check for both of the tanks :-) good results no leaks !!!
the tanks are done !!!
|
Tal
Yossi
Orlev |
1.0 |
21-03-2006
to
15-06-2006 |
Total time |
Yossi
Tal
Orlev |
79.5 |
Congratulation !!!!!!
We finished the fuel tanks
|
|
Wing Assembling
Date
|
Task Description |
Done By |
Hours |
12-06-2006 |
Debur dimple and machine countersink the W-919 joint plate
|
Tal |
2.0 |
13-06-2006 |
Finish the W-919 joint plate.
|
Tal |
1.0 |
15-06-2006 |
1 - machine countersink the main spar to accept the skin dimple.
2 - Deburring the leading edge ribs and skins.
|
Tal
Yossi
Orlev |
4.0 |
20-06-2006 |
Dimple the leading edge ribs and skins.
|
Tal
Yossi |
4.0 |
24-06-2006 |
Deburring the skeleton left ribs.
|
Yossi
Orlev |
2.5 |
25-06-2006 |
Deburring ...
|
Tal |
2.0 |
27-06-2006 |
Deburring ...
|
Tal |
3.0 |
30-06-2006 |
Deburring ... |
Yossi
Tal
Orlev |
4.0 |
01-07-2006 |
Deburring ... + Dimple
|
Tal |
3.0 |
02-07-2006 |
Deburring ... + Dimple
|
Tal |
1.0 |
03-07-2006 |
Deburring ... + Dimple
|
Tal |
3.0 |
07-07-2006 |
Deburring ... + Dimple |
Tal
Yossi
Orlev |
6.0 |
08-07-2006 |
Dimpling
|
Tal |
4.0 |
09-07-2006 |
Priming preparations
|
Tal |
1.0 |
10-07-2006 |
Priming
|
Tal |
5.5 |
14-07-2006 |
Final dimpling work
drilling hole in the ribs for conduit tube
|
Tal
Yossi
Orlev |
6.0 |
18-07-2006 |
Preparing parts for priming
Priming the wing ribs
|
Tal |
5.5 |
20-07-2006 |
Preparing the shop for riveting construction
Assembly & riveting the doubler plates to W-907 rear spar
|
Tal |
2.5 |
21-07-2006 |
Assembling and riveting the wing ribs to the W-906 wing front spare
assembly
|
Tal
Yossi
Orlev |
4.5 |
22-07-2006 |
Assembling and riveting the wing ribs to the W-907 wing rear spare
assembly
|
Tal |
4.0 |
11-08-2006 |
Riveting platenut on the W919 joint plate
|
Tal
Orlev |
1.0 |
15-08-2006 |
assembling and riveting left wing leading edge
|
Tal |
3.0 |
16-08-2006 |
assembling and riveting right wing leading edge
Yossi's work colleagues came to see the "first lady"
|
Tal
|
2.0 |
19-08-2006 |
Priming the wing skins
|
Tal |
4.0 |
20-08-2006 |
Priming the wing skins
|
Tal |
4.5 |
01-09-2006 |
Installing the tie down bracket on W-906.
Riveting right wing leading edge assembly to the W-906 front spare.
Assembly top skins on the right wing
First construction inspection by Shmuel Ozery
certified aviation engineer and chief inspector of "Maintenance 2000"
|
Tal
Yossi
Orlev |
3.0 |
09-09-2006 |
Riveting the right wing top skins
Grushka family visit |
Tal
Yossi
Orlev |
6.0 |
23-09-2006 |
Riveting left wing leading edge assembly to the W-906 front spare.
Riveting the left wing top inbd skins
|
Tal
Yossi
Orlev |
5.0 |
06-10-2006 |
Riveting the left wing top outbd skins
|
Yossi
Orlev |
4.0 |
09-10-2006 |
Finish the riveting work on left wing top skins
|
Yossi
Orlev |
4.0 |
24-10-2006 |
Disassembly the wings from the jig
Building the wing carter
|
Yossi
Tal |
6.0 |
28-10-2006 |
Assembling and drilling the aileron brackets W-914 & W-913.
Assembling and drilling the flaps brackets
W-925 .
|
Tal |
7.5 |
17-11-2006 |
Deburring aileron and flaps brackets.
Assembling and drilling the aileron gap fairing W-924 .
|
Yossi
Tal
Orlev |
3.0 |
18-11-2006 |
Assembling and drilling the flaps gap fairing W-921.
Painting preparations
|
Tal |
4.0 |
20-11-2006 |
Painting preparations
|
Tal |
3.0 |
21-11-2006 |
Priming the aileron & flaps hinges brackets
Priming the aileron & flaps fairings
|
Yossi
Tal |
3.0 |
23-11-2006 |
Riveting the W-913 and W-925 aileron and flaps wing hinges.
|
Yossi
Tal |
3.5 |
24-11-2006 |
Riveting the W-913 and W-925 aileron and flaps wing hinges.
Riveting W-924 and W-921 wing gap fairing
|
Yossi
Tal
Orlev |
6.0 |
28-11-2006 |
Amir Choen visit our shop and examine the working process.
|
Yossi
Tal
Orlev |
0.0 |
23-11-2006 |
Riveting the W-913 and W-925 aileron and flaps wing hinges.
|
Yossi
Tal |
3.5 |
12-06-2006
to
23-11-2006 |
Total time |
Yossi
Tal
Orlev |
144.5 |
Congratulation !!!!!!
We finished the Wings Assembling
|
|
Ailerons
Date
|
Task Description |
Done By |
Hours |
30-09-2006 |
Assembly both ailerons skeleton
|
Tal |
4.0 |
01-10-2006 |
Constructing both ailerons stiffeners
Match drilling the aileron left skins
Drilling the left W-909 counterbalance
|
Tal |
6.0 |
02-10-2006 |
Match drilling the aileron right skins
Drilling the right W-909 counterbalance
Parts deburring
|
Tal |
7.0 |
06-10-2006 |
Parts deburring and dimpling
|
Tal
Orlev |
4.0 |
09-10-2006 |
Parts dimpling
|
Tal
Orlev |
2.0 |
10-10-2006 |
Priming ailerons Parts
|
Tal |
3.5 |
16-10-2006 |
Assembling and riveting the ailerons
|
Tal
Yossi |
3.0 |
17-10-2006 |
Assembling and riveting the ailerons
|
Tal
Yossi |
3.0 |
19-10-2006 |
Match drilling the aileron trilling edge
|
Tal |
2.0 |
20-10-2006 |
Machine countersink the W-911 aileron trailing edge.
Preparing tools for trailing edge gluing process.
Gluing trailing edge with 3M-460
|
Tal
Yossi
Orlev |
5.5 |
26-10-2006 |
Disassembly the tool from the trailing edge.
Riveting the trailing edge.
|
Tal
Yossi |
2.5 |
28-11-2006 |
Left aileron and control push-rod assembled on the wing.
|
Yossi
Tal
Orlev |
3.0 |
08-12-2006 |
Ailerons push-rod trimming and cutting.
|
Yossi |
3.0 |
17-02-2007 |
Fabricate A-914 control stoper
|
Tal |
2 |
30-09-2006
to
17-02-2007 |
Total time |
Yossi
Tal
Orlev |
50.5 |
Congratulation !!!!!!
We finished the ailerons
|
|
Flaps
Date
|
Task Description |
Done By |
Hours |
23-11-2006
to
28-11-2006 |
Fabricate the FL-907 and FL-906.
Assembly the FL-904 nose ribs and FL-907 hinge brackets.
Upper flap skin assembled.
|
Tal
Yossi |
6.0 |
30-11-2006 |
Fabricate flap assembly jig.
|
Yossi
Tal |
4.0 |
08-12-2006 |
Left flap match drilling.
|
Tal |
3.0 |
09-12-2006 |
Right flap assembled.
|
Yossi
Tal
Orlev |
3.0 |
11-12-2006 |
Right flap match drilling.
Right flap deburring.
|
Tal |
3.0 |
13-12-2006 |
1 - Finish Right flap deburring and dimpling
2 - Start Left flap deburring.
3 - Assemble a cabin from shipment box
for the large parts.
|
Yossi
Tal |
11 |
15-12-2006 |
Finish all deburring and dimpling
|
Yossi
Tal
Yair |
3 |
18-12-2006 |
Priming all parts
|
Tal |
5.5 |
19-12-2006 |
End of priming work on flaps parts
|
Tal |
1.5 |
22-12-2006 |
1 - assembling and riveting both of the flaps skeletons.
|
Tal |
4.5 |
29-12-2006 |
Assembling and riveting upper skins.
|
Tal |
2 |
26-01-2007 |
Riveting upper skin to main spar and ribs.
|
Yossi
Tal |
5 |
02-02-2007 |
1 - Riveting bottom skin to main spar and ribs
2 - Glue the skins (upper & lower) trialing edge and FL-909 with 3M-460
epoxy glue
|
Yossi
Tal
Orlev |
4 |
11-02-2007 |
1 - Riveting right flaps trailing edge
2 - Riveting bottom left skins to main spar and ribs
2 - Glue the skins (upper & lower) trialing edge and FL-909 with 3M-460
epoxy glue
|
Yossi
Tal
Orlev |
5 |
17-02-2007 |
1 - Riveting left flaps trailing edge
|
Yossi
Tal
Orlev |
2 |
23-11-2006
to
17-02-2007 |
Total time |
Yossi
Tal
Orlev |
62.5 |
Congratulation !!!!!!
We finished the Flaps
|
|
Miscellaneous
Date
|
Task Description |
Done By |
Hours |
20-05-2006 |
Assembling the mounting hardware for the heated pitot probe.
|
Tal
Oved |
6.0 |
27-05-2006 |
1 - Modify and assembly the AOA Sport static probes in the outer bay of
the left wing.
2 - Fabricate and assembly taxi light in the outer bay of the left wing.
|
Tal
Oved |
6.5 |
30-05-2006 |
Fabricate and assembly taxi light in the outer bay of the right wing.
|
Tal |
2.5 |
31-05-2006 |
Finish fabricate and assembly taxi light in the outer bay of the right
wing.
|
Tal |
2.0 |
27-10-2007
to
01-10-2007 |
Assembly the wing tips Plexiglas Nav light cover
Riveting misc. parts
|
Tal |
7 |
10-11-2007 |
Fabricate Aileron BMA auto pilot servo bracket
|
Tal |
6 |
17-01-2008 |
Riveting Aileron
auto pilot servo bracket
|
Tal |
3 |
08-12-2009 |
Attaching the wings (Temporary) to fuselage to start with the final wing
tasks process
|
Tal
Yossi
Amir
Guy
|
3 |
18-12-2009 |
Measured
and align:
1 - Wing front line.
2 - Distance from wing edge (tip) to
aircraft
center line at the empennage reference point.
3 - Wing elevation
angle.
After measuring and re-measuring
we drilled the wing back attach bracket.
|
Tal
Yossi |
6 |
22-12-2009 |
Temporary
Installing aileron pushrods. (need final adjustment)
Installing Flaps pushrod. looks perfect
|
Tal
Yossi |
4 |
25-12-2009
to
22-01-2010 |
We are closing
many small tasks regarding Wing Fuselage
connection wiring and
plumbing
roots for electricity and pressure
tubing
Assemble
and remove the wings is now a easy routine after doing it for the fifth
time
|
Tal
Yossi |
14 |
12-03-2010 |
Preparing parts for painting:
Aileron pushrod Wing attaching brackets.
Painting wash primer first coat
|
Yossi
Tal
Orlev |
3 |
20-05-2006
to
12-03-2010 |
Total time till now |
Yossi
Tal
Orlev |
63 |
Congratulation !!!!!! |
|
Finishing
Date
|
Task Description |
Done By |
Hours |
18-05-2007
to
19-05-2007 |
Working on wing tips
|
Tal |
7 |
29-06-2007 |
Installing Left wing tip strobe and Nav light
Fabricate Left wing tip Nav light Plexiglas cover
|
Tal |
5.5 |
12-07-2007 |
Fabricate Right wing tip Nav light Plexiglas cover
|
Tal
|
2.5 |
02-10-2007 |
Working on wing tips
|
Tal
|
4 |
04-10-2007
to
10-10-2007 |
Working on wing tips
|
Tal
|
14.5 |
17-10-2007 |
Finish working on wing tips
|
Tal
|
6 |
04-04-2010 |
Removing the fuel tanks in order to complete paint job before final
attaching them back.
|
Tal
Orlev
Yossi |
1 |
11-06-2010
to
18-06-2010 |
Painting fuel tanks final
attaching them back.
Riveting right wing bottom sheets. This was the most fearing task but it
came out a very straight forward
easy task and
the results are fantastic. (we used a home made backing bar tool)
|
Tal
Orlev
Yossi |
10 |
25-06-2010 |
Riveting right wing bottom sheets.
|
Tal
Yossi |
7 |
18-05-2007
to
25-06-2010 |
Total time till now |
Yossi
Tal
Orlev |
57.5 |
Congratulation !!!!!! |
|
Fuselage (QB)
Steps and Landing
gear
Date
|
Task Description |
Done By |
Hours |
22-12-2006 |
Cutting out the holes for both steps
|
Yossi |
2 |
28-12-2006 |
1 - Finishing the right step
2 - Working on WD-921 right landing gear mount
|
Yossi |
6 |
29-12-2006 |
Working on WD-921 left landing gear mount
|
Yossi |
4 |
31-12-2006 |
Finishing the left step
|
Yossi |
2 |
17-02-2007 |
1 - Working on the L&R steps (Deburring)
2 - Assembling the W-611/617 control stick and disassembling it.
|
Tal
Yossi |
1.5 |
02-04-2007 |
Final match
and drill the landing gear mount (right side)
|
Tal
Yossi
Orlev |
2 |
03-04-2007 |
Final match and drill the landing gear mount (Left side)
|
Tal |
4 |
23-05-2007 |
Drilling the F-704 cap strip
WD-921 right landing gear mount final installation
|
Tal |
4 |
25-05-2007 |
WD-921 left landing gear mount final installation
Miscellanies riveting
Fitting the horizontal stabilizer
|
Tal
Yossi
Orlev |
7 |
07-10-2009 |
Final fastening and securing
main & nose wheel
assembly.
|
Tal
Yossi
Orlev |
4 |
31-03-2010
to
30-04-2010 |
Working on main gear cowls and fairings.
measure
and mark aircraft
center line on the floor, adjust main gear cowls
parallel
to center line
|
Tal
Yossi
Orlev |
43 |
30-06-2010 |
Working on main gear fairings. Fabricating and gluing the main gear
stiffener.
|
Tal
Yossi
|
2 |
19-12-2006
to
30-04-2010 |
Total time till now |
Yossi
Tal
Orlev |
81.5 |
Congratulation !!!!!! |
|
Seat backs
Date
|
Task Description |
Done By |
Hours |
09-03-2007 |
1 - Working on forward seat floors and control rod tunnel.
2 - Working on seat backs
|
Tal
Yossi
Orlev |
2 |
16-03-2007 |
Working on seat backs
|
Yossi
|
4 |
21-03-2007 |
Drill seat backs and hinges (L&R)
|
Yossi
|
5 |
24-03-2007 |
Drill seat back brace
|
Yossi
Orlev |
1 |
27-03-2007 |
Deburr all seat back parts.
|
Yossi |
3 |
13-04-2007 |
Riveting the seat backs
Installing brake master cylinder
|
Tal
Yossi
Orlev |
4.5 |
02-11-2007 |
After all the work we ordered the Classic Aero Aviator Interior kit.
(see next chapter)
|
|
0 |
09-03-2007
to
02-11-2007 |
Total time till now |
Yossi
Tal
Orlev |
19.5 |
Congratulation !!!!!! |
|
Fuel Brake & Rudder assembly
Date
|
Task Description |
Done By |
Hours |
23-02-2007 |
1 - Assemble the F-6117 L&R brake pedals
2 - Assemble the WD-655 and F-6116 side bearing
blocks
|
Yossi
Tal
Orlev |
6.5 |
02-03-2007 |
1 - Fitting the aft top skin of the fuse
2 - Installing Rudder and Brake pedals
|
Tal
Yossi |
4 |
08-04-2007 |
Riveting and assembly brake pedals
|
Tal |
3 |
13-04-2007 |
Installing brake master cylinder
|
Tal
Yossi
Orlev |
4.5 |
09-05-2007 |
Enlarge holes in fuselage for fuel and vent line
|
Yossi |
3 |
11-05-2007 |
Working on fuel and vent line inside the fuselage
|
Yossi
Orlev |
8 |
12-05-2007 |
Fabricate F-966 L&R fuel tank attach bracket
Working on VA-106 Gascolator Reinf bracket
Working on fresh air intake assembly
|
Tal |
8 |
22-05-2007 |
Working on fuel and brakes lines
|
Yossi
Orlev |
7 |
08-10-2008
to
16-10-2008 |
Final assembly the brakes pedals
Fuel and vent line installation
Installing marker beacon and transponder antenna
Working on Safe Air 1 static port installation kit
|
Tal
Yossi |
16 |
15-11-2008 |
Installing outer brakes line
|
Tal |
4 |
18-11-2008 |
Installing "Bonaco" upgraded brakes lines kit
Riveting upper forward fuselage section
|
Yossi
Orlev |
5.5 |
07-10-2009 |
Final
Installing the fuel selector.
|
Tal
Yossi
Orlev |
2.5 |
23-02-2007
to
07-10-2009 |
Total time till now |
Yossi
Tal
Orlev |
72 |
Congratulation !!!!!! |
|
Empennage Attaching
Date
|
Task Description |
Done By |
Hours |
25-05-2007 |
Fitting the horizontal stabilizer
|
Tal
Yossi
Orlev |
7 |
26-05-2007 |
Fabricate F-989 Elevator pushrod
Installing F-635 bell crank
Installing control stick assembly
|
Tal |
5.5 |
01-06-2007 |
Fitting the vertical stabilizer
|
Tal
Yossi
Orlev |
5 |
08-06-2007 |
Fabricate F-790 Elevator pushrod
Installing Rudder cables
|
Tal
Yossi
Orlev |
4 |
15-06-2007 |
Working on Aileron trim servo mechanism
Fabricate F-792 rudder stop
|
Tal
Yossi
Orlev |
5 |
18-04-2008 |
Riveting the elevator short pushrod
|
Yossi
Tal |
1 |
25-05-2007
to
18-04-2008 |
Total time till now |
Yossi
Tal
Orlev |
27.5 |
Congratulation !!!!!! |
|
Instrument Panel
Date
|
Task Description |
Done By |
Hours |
12-07-2007
to
28-07-2007 |
Working on the front deck and
instrument panel
|
Tal
Yossi
|
24 |
10-08-2007 |
Working on the instrument panel
|
Yossi
Tal |
12 |
13-08-2007 |
Working on the front deck
|
Tal |
3 |
17-08-2007 |
Priming parts
|
Yossi
Tal |
7 |
19-08-2007
to
23-08-2007 |
Riveting the instrument panel
Installing the forward fuselage ribs
|
Tal |
15 |
22-02-2008
to
29-02-2008 |
Working on instrument NAV/COM frames
|
Yossi
Tal
Orlev |
3.5 |
07-03-2008
to
11-03-2008 |
Working on instrument NAV/COM frames
|
Yossi
Tal
Orlev |
3.5 |
14-03-2008
to
18-03-2008 |
Fabricating a plywood instrument panel for
final layout planning. |
Yossi
Orlev |
13.5 |
30-09-2008
to
03-10-2008 |
Working on baggage floor
Riveting canopy latch side handle bracket
Installing power Terminal Bus under the seat skins
Firewall forward installations
ELT & Strobe PS installations & wiring
Misc wiring
|
Yossi
Tal
Orlev |
22.5 |
11-10-2008
to
13-10-2008 |
Installing VHF antennas
Working on wiring and cabin components
|
Yossi
Tal |
8 |
19-10-2008
to
20-10-2008 |
Wiring sticks switches
Fabricate avionics flip flop brackets
Installing static port tube
|
Yossi
Tal |
13 |
24-10-2008
to
01-11-2008 |
Wiring
Fabricating bottom instrument panel mockup
|
Yossi
Tal |
12 |
12-11-2008 |
Dimmer Drawer
Baggage and map LED light
|
Yossi
Tal |
6.5 |
14-11-2008 |
Disassembling the panel construction for paint
Fabricate circuit bracer hub bracket
Avionics component layout setup
|
Yossi
Tal |
5 |
15-11-2008 |
Priming panel parts
|
Tal
|
1 |
21-11-2008 |
Rivet front instrument structure
to fuselage
body.
Rivet antenna stiffeners plate to fuselage body
Reassembling the instrument stack
Assembling GPS antennas on upper dashboard skin.
|
Yossi
Tal
Orlev |
7 |
24-11-2008 |
Final align and fasten
the instrument stack
Working on left instrument tray,
assembling
the FPS-Plus and Relay boards.
|
Yossi |
3 |
25-11-2008 |
Working on left instrument tray,
adding wire tie elements.
Assembling the fuse block bracket behind the EFIS/Lite Sport G4
unit.
Drilling holes for cable root on left side for Advanced AF-3400
connectors.
|
Yossi |
4 |
06-03-2009 |
Assembling all elements on the panels: switches, circuit breakers and
all instruments. Looks perfect.
|
Yossi |
5 |
05-03-2010
to
12-03-2010 |
Fabricating and installing a distribution block for the Static and Total tubes.
|
Tal |
6 |
12-07-2007
to
12-03-2010 |
Total time till now |
Yossi
Tal
Orlev |
174.5 |
Congratulation !!!!!! |
|
Electrical Wiring
Date
|
Task Description |
Done By |
Hours |
02-04-2007 |
Electric flaps assembly (we got
a wrong motor …)
|
Tal
Yossi
Orlev |
1 |
27-04-2007 |
Working on the flaps electric motor
|
Yossi |
4 |
04-05-2007 |
Working on the flaps electric motor
Drilling holes for the static ports
Installing the 5th point for the seat belt
|
Tal
Yossi
Orlev |
6 |
18-06-2007 |
Installing Aileron trim servo assembly
Installing Elevator trim servo and push rod
|
Tal |
3 |
22-06-2007 |
Fabricate ELT bench
|
Yossi |
4 |
29-06-2007 |
Installing electrical flaps assembly and mounting the RC-Allen flaps
position sensor
|
Yossi |
5.5 |
21-09-2007
to
01-10-2007 |
Start to fabricate BMA elevator auto pilot servo
|
Yossi
Orlev |
23 |
03-10-2007 |
Fabricate BMA
Magnetometer bracket Finish Fabricate BMA auto pilot Elevator servo
bracket
Fabricate BMA Magnetometer bracket
|
Yossi
Orlev |
7.5 |
30-11-2007 |
Installing Starter
and Master Solenoid
|
Yossi |
1 |
15-12-2007 |
Finish the canopy
release mechanism
Deburing and Dimpling F-704 AFT top skin
|
Yossi
Tal
Orlev |
5.5 |
20-01-2008
to
24-03-2008 |
Wire and test the Flap Positioning System (FPS-Plus
By Aircraft Extras)
|
Yossi |
20 |
02-05-2008 |
Fixing the Pos-12 position sensor to be in center with the flap arm.
Drilling hole in the ribs for conduit tube from the Empennage to the
instrument panel
|
Yossi |
6 |
10-05-2008 |
Installing the
conduit tube with wires for the Elevator trim and the
back view camera.
|
Yossi |
4 |
26-06-2008
|
Preparing the sticks (length and holes for wiring)
|
Yossi |
2 |
08-07-2008 |
Wiring the stick grips.
|
Yossi |
2 |
30-09-2008 |
Installing
power Terminal Bus under the seat skins |
Yossi |
2 |
01-10-2008 |
ELT & Strobe PS
installations & wiring
|
Yossi |
4 |
03-10-2008
to
20-10-2008 |
Sticks wiring
|
Yossi |
25 |
06-11-2008
to
11-11-2008 |
Arranging Electrical equipments placement.
|
Yossi
Tal |
12 |
28-11-2008 |
Wiring the Dimmer
Drawer
assembly.
Working on left instrument tray,
adding D-Type connectors.
|
Yossi |
6 |
02-12-2008 |
Wiring the left instrument tray.
|
Yossi |
5 |
05-12-2008
to
12-12-2008 |
Identifying and Marking empennage Elevator trim Wires.
Wiring left instrument
tray
connectors (D Type 25 pin)
|
Yossi |
5 |
16-12-2008 |
Final wiring left instrument
tray
connectors.
Connecting power and testing operation of Flaps, Elevator Trim and
Aileron Trim. Testing functionality of all switches involved.
All working according to plan.
|
Yossi |
5 |
19-12-2008 |
Connecting the AF-3400 Trim Power (pin 2 ,10Volts) and Flap,
Elevator, Aileron Trims (pins 34,35,36 ) to the FPS-Plus system.
Performing a full system test with all elements involved.
Programming the FPS_plus for 5 Flaps stops with associated Elevator
trims. Calibrating the AF-3400 Flaps and Trim indicators to show the
programmed flap/trim stops.
Testing Min/Max range for all elements.
All working according to plan.
See Note 1 on Drawing #4 (Flap
System ( Fps), Relays, Controls, Sticks and Motors)
for AF-3400 / FPS-Plus Voltage difference solution
|
Yossi |
4 |
26-12-2008 |
Installing Electrical equipments on
right instrument tray.
|
Yossi |
4 |
29-12-2008 |
Fabricating small brackets for cable tie down.
Drilling holes and Preparing platenuts
to hold the
instrument trays.
|
Yossi
Tal |
6 |
02-01-2009 |
Installing platenuts to hold the
instrument trays.
|
Yossi
Tal |
3 |
31-01-2009 |
Fabricating a isolated plate for the
diodes and installing them on back of the right side panel.
|
Yossi
Tal |
4 |
03-02-2009 |
Connecting wires from main & starter Contactors into the panel.
|
Yossi |
2 |
17-02-2009 |
Wiring the diodes D1 & D2 to relays R1 & R2, leaving 2 wires to be
connected later to Master & Avionics switches
|
Yossi |
1 |
10-03-2009 |
Wiring some switches with there circuit breakers.
After installing the right side instrument panel we decided to relocate
the diodes and relay differently to have more space for maintenance.
working on wire rooting.
|
Yossi |
12 |
12-03-2009
to
28-03-2009 |
Wiring avionics power and ground to power and ground busses.
Turn ON all units one by one to check wiring. all units turned on OK
including FPS.
. |
Yossi |
30 |
31-03-2009
to
17-04-2009 |
Wiring lights power and ground to power and ground busses.
Wire and test the DCU . works OK
Wire the Map and baggage lights.
|
Yossi |
56 |
01-05-2009 |
Wiring Molex connectors for the nav and strobe lights. Start the strobe power
supply for the first time with a reduced power as advised by Whelen.
Check nav and strobe all works OK.
|
Yossi |
2 |
08-05-2009
to
03-07-2009 |
Adding a micro Switch to control luggage
light and canopy latch warning
through the AF-3400 voice
announcement.
Adding a Flaps position detector for
the AOA system
|
Yossi |
24 |
17-07-2009 |
Wiring the FPS program switch and LED to a connector behind the
instrument panel for in-flight FPS
calibration.
|
Yossi |
4 |
13-10-2009
to
19-10-2009 |
Wiring VOR & Camera coax & power wires.
|
Yossi |
4 |
31-10-2009 |
Routing Cabin light wires to the cabins left/right side covers,
soldering Mic./Headphone wires to final location. Routing Nav. Taxi,
landing and Pitot heat wires to left/right wing access.
|
Yossi |
4 |
03-11-2009
to
17-11-2009 |
Assemble BNC connectors on all coax cables.
|
Yossi |
8.5 |
04-12-2009 |
Combining the audio from AF-3400 EMS and AOA
with a resistor net into the GMA340 Audio Panel
|
Yossi |
1 |
22-01-2010 |
Implementing the music input to the GMA340 audio panel with the 20db
option active.
|
Yossi |
2 |
29-01-2010
to
26-02-2010 |
Assemble Connectors on fuselage side wing side and lights end. for wings lights , strobe and Pitot
heat.
|
Yossi |
12 |
05-03-2010 |
Assemble Connectors on Empennage end for Strobe and Nav. lights
Fabricate a plate to install the fuel transducers behind the instrument
panel
|
Yossi |
3 |
12-03-2010 |
Routing wiring (power & I/O) to fuel
capacity transducers
|
Yossi |
2 |
12-03-2010 |
Wiring (power & I/O) fuel
capacity transducers
|
Yossi |
2 |
20-07-2010 |
Wiring all electrical chassis on instrument trays to airframe.
|
Yossi |
2 |
02-04-2007
to
20-07-2010 |
Total time till now |
Yossi
Tal
Orlev |
351 |
Congratulation !!!!!! |
|
Wings Attaching
Date
|
Task Description |
Done By |
Hours |
|
|
|
0 |
|
Total time till now |
Yossi
Tal
Orlev |
0 |
See Final Push |
|
Miscellaneous
Date
|
Task Description |
Done By |
Hours |
05-04-2007 |
Preparing parts for painting: brake pedals, forward covers, seat backs.
Painting wash primer first coat
|
Tal |
7 |
06-04-2007 |
Painting Epoxy primer on brake pedals, forward covers, seat backs
Cleaning & preparing the forward fuselage for Epoxy primer painting
|
Tal
Orlev |
5 |
08-04-2007 |
Painting Epoxy primer on the forward fuselage
|
Tal |
3 |
28-04-2007 |
Assembly the F-635
elevator bell crank
Fabricate the F-9110 L & R stick boot ring
|
Tal |
3 |
04-05-2007 |
Drilling holes for the static ports
Installing the 5th point for the seat belt
|
Tal
Yossi
Orlev |
6 |
09-05-2007 |
Working on Aft tie down bar
|
Yossi |
3 |
18-05-2007 |
Preparing & priming
miscellaneous parts
|
Tal |
3 |
22-05-2007 |
Riveting flap assembly, F-635 elevator bellcrank and AFT tie down bar
|
Yossi
Orlev |
7 |
01-06-2007 |
Modify and Fabricate the cockpit fresh air intake
|
Tal
Yossi
Orlev |
5 |
04-10-2008 |
Painting fuselage forward section
|
Tal |
2.5 |
12-10-2007 |
Working on F-824B cover plate
Fabricate Rudder cable cover
|
Tal |
3 |
19-10-2007 |
Finish F-824B cover plate
|
Tal |
5 |
20-10-2007 |
Preparation for paint masc. parts
|
Tal |
8.5 |
23-10-2007 |
Preparation for paint masc. parts
|
Tal
Orlev |
3 |
26-10-2007 |
Priming Fuselage center section and misc.
parts
|
Tal |
5 |
02-11-2007 |
Riveting
Misc. parts
|
Yossi
Tal
Orlev |
5.5 |
04-01-2008
to
05-01-2008 |
Fuselage forward section Dissemble and Preparation parts for paint
|
Yossi
Tal
Orlev |
8 |
08-01-2008 |
Priming Fuselage
forward section parts and Misc. parts
|
Yossi
Tal
Orlev |
6 |
11-01-2008 |
Riveting the front
deck section
|
Yossi
Tal
Orlev |
4.5 |
26-06-2008
to
28-06-2008 |
Installing the
hinges on the "Classic Aero"
seat backs
Preparing and installing the main and nose landing gear.
The
Plane
is now on wheels
|
Yossi
Tal
Orlev |
15 |
09-07-2008 |
Painting cabin visible parts to there final color (light gray).
|
Tal
|
3 |
15-08-2008 |
Mounting bracket for the Whelen strobe power supply and the meri-King
ELT in a standardized location as instructed in the kit.
|
Tal
Orlev |
4 |
02-07-2010 |
Rivet aft top skin.
|
Tal
Yossi |
4 |
05-04-2007
to
02-07-2010 |
Total time till now |
Yossi
Tal
Orlev |
119 |
Congratulation !!!!!! |
|
Finish Kit
Cabin Covers and Interior
Date
|
Task Description |
Done By |
Hours |
02-04-2007 |
Working on the forward covers
|
Tal
Yossi
Orlev |
2 |
03-04-2007 |
Drill deburr and dimple all forward covers
|
Tal |
4 |
08-04-2007 |
Riveting and assembly forward covers and brake pedals
|
Tal |
3 |
02-11-2007 |
Classic Aero Aviator Interior kit has arrived …. AMAZING WORK !!!
|
|
0 |
12-07-2008 |
Painting some
cockpit part Grey color
|
Tal |
2.5 |
30-09-2008
to
03-10-2008 |
Working on baggage floor
Firewall forward installations
|
Tal
Yossi
Orlev |
17 |
04-10-2008 |
Painting fuselage forward section
|
Tal
|
2.5 |
08-10-2008 |
Final assembly the brakes pedals
Fuel and vent line installation
|
Tal
Yossi
|
6 |
10-03-2009 |
Working on baggage floor. replacing rivets with platenuts
.
|
Tal |
3 |
13-03-2009 |
Preparing cabin for final paint.
|
Tal
Orlev |
5 |
17-03-2009 |
Painting cabin inside final color. (light
gray)
|
Tal
Yossi |
3 |
30-07-2010 |
Modify interior left side panel to accept the modified opening handle.
Install and wire the cabin flood light on side panels.
|
Yossi |
2 |
02-04-2007
to
30-07-2010 |
Total time till now |
Yossi
Tal
Orlev |
50 |
Congratulation !!!!!! |
|
Tip Up Canopy
Date
|
Task Description |
Done By |
Hours |
06-07-2007 |
Fabricate brackets
for cabin frame
|
Yossi |
4 |
12-07-2007
to
27-07-2007 |
Constructing the cabin frame
|
Tal
Yossi
|
14 |
30-07-2007 |
Scrape cabin frame brackets to fit
fuselage outer layout
Drill cabin frame brackets to fuselage
|
Yossi |
4 |
09-08-2007 |
Constructing the cabin frame
|
Yossi |
5 |
10-08-2007 |
Deburr the cabin frame
|
Yossi
Tal |
12 |
17-08-2007 |
Priming parts
|
Yossi
Tal |
7 |
19-08-2007
to
23-08-2007 |
Installing the canopy release mechanism
|
Tal |
15 |
24-08-2007 |
Riveting the cabin frame
Installing the side handle
|
Yossi
Tal |
4 |
25-08-2007 |
Installing the side handle
Installing
the AFT canopy latch
|
Tal |
7 |
26-08-2007
to
27-08-2007 |
Fitting the canopy
frame to the fuselage and cabin frame
|
Tal |
7 |
31-08-2007 |
Fitting the canopy frame to the fuselage
and cabin frame
Trimming the
Plexiglas canopy bubble – we messed-up the canopy and we need to order
new one ….
LLL
|
Yossi
Tal |
6 |
03-11-2007 |
Working on canopy release mechanism
|
Tal |
4 |
14-11-2007 |
Working on canopy
frame
|
Tal |
2.5 |
25-11-2007 |
Deburing canopy frame
|
Tal |
4 |
30-11-2007 |
First Trimming to
the new Plexiglas canopy bubble
|
Yossi
Tal
Orlev |
6 |
15-12-2007 |
Finish the canopy
release mechanism
Deburing and Dimpling F-704 AFT top skin
|
Yossi
Tal
Orlev |
5.5 |
18-01-2008 |
Trimming the canopy Bubble
Splitting the canopy to front and back parts
|
Yossi
Tal
Orlev |
5 |
25-01-2008
to
01-02-2008 |
Drilling the canopy bubble with the frame
|
Yossi
Tal
Orlev |
4.5 |
04-02-2008
to
05-02-2008 |
Working on the new
upgraded canopy latch side handle
Deburing
and
Countersink the canopy bubble
|
Yossi
Tal
Orlev |
6 |
08-02-2008 |
Working on the tip up stiffeners and
side handle |
Yossi
Tal
Orlev |
5.5 |
15-02-2008 |
Preparing stiffeners for painting |
Yossi
Tal
Orlev |
3 |
22-02-2008
to
29-02-2008 |
Priming canopy parts
|
Yossi
Tal
Orlev |
3.5 |
07-03-2008
to
11-03-2008 |
Riveting the tip up stiffeners
|
Yossi
Tal
Orlev |
3.5 |
21-03-2008 |
Working on the side cover of the canopy
|
Yossi
Tal |
5 |
26-06-2008
to
28-06-2008 |
Rivet and finish the tip up frame. (it is now ready to install
the bubble).
Preparing the sticks (length and holes for wiring)
Installing the hinges on the "Classic
Aero" seat backs
Preparing and installing the main and nose landing gear.
The
Plane
is now on wheels
|
Yossi
Tal
Orlev |
20 |
04-07-2008 |
Fabricate and install a cover strip on the tip up.
Install the tip up
piston on the fuselage.
|
Yossi
Tal
Orlev |
5 |
08-07-2008 |
Working on the tip up locking mechanism.
Wiring the stick grips.
|
Yossi
Tal
|
4 |
08-07-2008 |
Working on the tip up locking mechanism.
Cutting
Plexiglas
bubble aft side to final size.
|
Yossi
Tal
Orlev |
5 |
18-07-2008 |
Working on the back canopy part. cutting the
Plexiglas,
match drilling all
Plexiglas
attaching holes
through the back cover sheet and bridge.
|
Yossi
Tal
Orlev |
5.5 |
31-07-2008 |
Working on the back canopy part. Machine countersink all
Plexiglas
attaching holes, Dimple
the back cover sheet and
thread
holes in the bridge.
|
Yossi
Tal
|
3 |
30-09-2008 |
Riveting canopy latch side handle bracket
|
Yossi
Tal
|
.5 |
25-11-2008 |
Preparing canopy frame for paint.
|
Tal |
2 |
28-11-2008 |
Paint inside canopy gray final color, prepare the outside for painting.
|
Tal |
6 |
29-11-2008 |
Paint upper canopy primary
gray color.
|
Tal |
1 |
02-12-2008 |
Paint upper inside canopy black final color.
|
Tal |
2.5 |
05-12-2008
to
12-12-2008 |
Attach Plexiglas bubble
to canopy frame and
glue the front babble to skin.
|
Yossi
Tal
Orlev |
9 |
16-12-2008
to
19-12-2008 |
Smooth the
front babble to skin
glue area. Prepare for final polish.
|
Tal |
7 |
24-07-2009
to
27-03-2009 |
Final assembling the tip up locking
handle mechanism.
|
Tal |
5 |
23-07-2010
to
30-07-2010 |
Assembling back babble, final trimming the
join edges of front ant back babbles.
Final assembling the metal overlap strip on the aft tip up babble
|
Tal
Yossi
Orlev |
10 |
06-07-2007
to
30-07-2010 |
Total time till now |
Yossi
Tal
Orlev |
228.5 |
Congratulation !!!!!! |
|
Cowl
Spinner & Wheel Fairings
Date
|
Task Description |
Done By |
Hours |
10-02-2009 |
Start learning the next task
baffling
and
cowl.
|
Yossi
Tal |
1 |
13-02-2009 |
Working on top cowl, Attaching the cowl to propeller back plate with
distance bocks marking and cutting the back end to fit with the upper
front cover sheet.
|
Yossi
Tal
Orlev |
4 |
17-02-2009 |
Matching two halves together to get a perfect circle for the spinner.
Cutting a slot for the nose gear.
Began fitting the lower cowl.
|
Yossi
Tal |
2 |
20-02-2009
to
03-03-2009 |
Working on the cowl upper and lower support strips.
Fine Fitting upper cowl to firewall.
Fitting lower cowl to firewall and upper cowl
|
Yossi
Tal |
16 |
13-03-2009
to
27-03-2009 |
Working on the oil check door on the upper cowl |
Orlev
Tal |
6 |
10-04-2009
to
17-04-2009 |
Working on the oil check door on the upper cowl
Working on the support strips between upper and lower cowl.
Enlarging all holes on support strips for the
Dzus
elements.
|
Orlev
Tal
Yossi
|
24 |
01-05-2009 |
Installing the Dzus
fasteners springs
|
Orlev
Tal
Yossi |
4 |
19-10-2009 |
Trimming the spinner to fit on the propeller.
|
Tal
Yossi |
2 |
27-10-2009
to
31-10-2009 |
Working on spinner.
Installing platnuts on spinner plates.
Adding a layer of fiberglass inside the spinner to fit to the front
propeller plate.
|
Tal
Yossi |
12 |
03-11-2009
to
17-11-2009 |
Fabricating an adjunct plate on the
propeller rear plate to close the propeller spinner back gap.
working on cowl engine air intake.
|
Tal
|
8 |
04-12-2009 |
working on cowl engine air intake.
|
Tal
|
2 |
06-07-2007
to
04-12-2009 |
Total time till now |
Yossi
Tal
Orlev |
81 |
Congratulation !!!!!! |
|
Paint
Date |
Task Description |
Done By |
Hours |
11-08-2010
to
16-08-2010 |
Preparing the plane to move to the paint room.
Disassembling the Empennage from Fuselage ( Elevator, Rudder, V/H
stabilizers)
Disassembling the propeller and all parts that have to be painted
separately
|
Orlev
Tal
Yossi |
26 |
16-08-2010 |
Moving to the paint room.
Start to arrange all parts for the paint process.
|
Orlev
Tal
Yossi |
8 |
17-08-2010
to
15-09-2010 |
Start with the paint process (sanding,
primary color; first coat of paint and
shellac)
At this point 2 dear friends joint the team Guy and Itay.
Guy is a aircraft builder with a lot of experience in the paint job.
Itay is a graphical designer.
All together night after night (6 hours every day) usually starting at
6pm into the night and the plane transformed from aluminum sheets into a
beautiful aircraft.
|
Orlev
Tal
Yossi
Guy
Itay |
270 |
11-08-2010
to
15-09-2010 |
Total time till now |
Yossi
Tal
Orlev |
304 |
Congratulation !!!!!! |
|
Miscellaneous
Date |
Task Description |
Done By |
Hours |
|
|
|
|
05-04-2007
to Now |
Total time till now |
Yossi
Tal
Orlev |
0 |
Congratulation !!!!!! |
|
Engine & Firewall
Date
|
Task Description |
Done By |
Hours |
19-12-2006 |
Working on the firewall
|
Yossi
Orlev |
6 |
23-05-2007 |
Engine preservation
|
Tal |
4 |
28-06-2008 |
Installing the engine Mount.
Installing the engine.
Observing and Marking all excess holes on firewall
|
Yossi
Tal
Orlev |
8 |
11-10-2008
to
13-10-2008 |
Removing the engine & mount from firewall
Installing FF components (battery try, cabin heat inlet door, master and
starter relay, firewall access holes)
|
Yossi
Tal |
8 |
26-12-2008
to
29-12-2008 |
Fabricating a bracket for the new Gascolator.
Matching the holes on the firewall for the new Gascolator bracket.
|
Tal |
6 |
31-01-2009 |
Installing back the engine & mount to find out were and how to route
the Engine sensors.
|
Yossi
Tal |
1 |
03-02-2009 |
Removing the engine & mount from firewall
starting work on Oil system drilling and installing platnuts.
|
Yossi
Tal |
4 |
06-02-2009 |
BIG BIG Day
Shmuel Ozery our process inspector visit for a
regular inspection. right after the inspection we started
together to
work on the engine. we started by taking out the engine from the
preservation and then completed all sensors attaching including
Alternator, Carburetor, Oil measuring stick and Oil pressure
|
Shmuel
Yossi
Tal |
5 |
10-02-2009 |
Mounting back the engine to firewall and connecting all
tubing and
wires between engine and firewall.
Attaching the propeller to engine pulley
|
Yossi
Tal |
6 |
08-05-2009
to
03-07-2009 |
Working on engine baffles |
Orlev
Tal |
24 |
17-07-2009 |
Working on engine baffles & air
filter |
Tal |
4 |
04-08-2009
to
07-08-2009 |
Wiring EMS sensors.
Installing protection diode on master/starter solenoids.
|
Yossi
|
8 |
14-08-2009
to
28-08-2009 |
Install EGT/CHT sensors, install connector's to other sensors.
Priming & painting
air filter parts.
Installing the pushrods.
|
Yossi
Tal |
24 |
04-09-2009
to
02-10-2009 |
Finalizing various tasks in order to START the Engine on the firs week
of October.
Main tasks are close and double
check all
electrical wiring ,Fuel pipes, Oil pipes
torque and mark
all bolts and screw-nut.
|
Yossi
Tal
Orlev |
30 |
04-10-2009
to
08-10-2009 |
Finalizing all engine tasks for first startup on Friday.
Closing and securing all Empennage and Fuselage covers.
|
Yossi
Tal
Orlev |
60 |
09-10-2009 |
First Engine Startup as
schedule.
Mr. Shmuel Ozeri (Maintenance 2000 LTD) examined the
entire project with a special focus on Engine.
We assembled the propeller adjusted the alternator belt and secured all
involved bolts for first startup.
Then we performed all necessary steps to
rinse the fuel system and build up the oil pressure (by hand)
At 14:16 we started the Engine for the first
time
WORKED
excellent
!!!!!
All EMS sensors read good readings, the idle needed a
little adjustment .
|
Yossi
Tal
Orlev
Shmuel |
8 |
31-10-2009 |
Routine engine start for 10 min, all
EMS sensors reading normal, the charge current starts high (40 amps) and
drops after 5 min to 17 amps.
|
Yossi
Tal |
1 |
04-12-2009 |
Routine engine start for 10 min.
The Spinner was installed on this start for the first time, Looks good
very smooth spinning.
|
Yossi
Tal |
1 |
22-01-2010 |
Routine engine start for 20 min.
|
Yossi
Tal |
1 |
30-04-2010 |
Routine engine start for 15 min.
|
Yossi
Tal |
1 |
11-06-2010 |
Routine engine start for 20 min.
|
Yossi
Orlev
Tal |
1 |
11-08-2010 |
Routine engine start for 12 min.
|
Yossi
Orlev
Tal |
1 |
23-05-2007
to
16-09-2010 |
Total time till now |
Yossi
Tal
Orlev |
212 |
Congratulation !!!!!! |
|
Avionic
Instruments & Panel
Date
|
Task Description |
Done By |
Hours |
19-11-2006 |
Avionic instruments
arrived:
1 - Garmin GNS-430
GPS/NAV/COM FAA TSO
2 - Garmin SL-30
NAV/COM FAA TSO
3 - Garmin GTX-327
Digital Transponder FAA TSO
4 - Garmin GMA-340 Audio
Panel / Intercom FAA TSO
5 - Garmin GI-106A X2 VOR/LOC/GS/CDI FAA
TSO
|
|
|
17-04-2007
to
24-04-2007
|
During the visit in "Sun 'n Fun" we decided on a new instrument panel
concept. The new concept will not be "IFR" and will be based on EIFS as
the main system with traditional devices as backup
as a result of that decision we
orderd:
Blue Mountain:
(Main EIFS & Autopilot)
1-
EFIS Sport G4
2 -Digital Autopilot
Advanced Flight Systems: (Engine monitoring Plus)
1 - AF-3400SP -
Sport System (Engine monitoring plus altitude, airspeed, VS)
2 - AF-4CYL - 4 Cylinder Sensor Pack
|
|
|
13-08-2007 |
BMA EFIS Sport is here + Autopilot system
|
|
|
12-10-2007 |
BMA is alive ….
J
|
Yossi
Tal
Orlev |
6 |
19-10-2007 |
Avionics check on test bench
|
Yossi
Tal
Orlev |
8.5 |
25-10-2007 |
Avionics check on test bench
Garmin 340 Audio panel is operating well ….
|
Yossi |
3 |
31-10-2007 |
Garmin 430 IFR GPS NAV COM in alive ….
|
Yossi |
1 |
14-03-2008
to
18-03-2008 |
Constructing a plywood mockup to plan the final placement for the
instrument panel left side
|
Yossi
Orlev |
4 |
08-07-2008 |
Constructing a plywood mockup to plan the final placement for the
instrument panel right side
|
Yossi
Orlev |
2 |
19-11-2006
to
08-07-2008 |
Total time till now |
Yossi
Tal
Orlev |
24.5 |
Congratulation !!!!!! |
|
Final Push
Date
|
Task Description |
Done By |
Hours |
16-09-2010 |
Today we moved back from the paint job into our
workshop.
From now until the first flight we will log all activities on this
section regardless the part we are working on.
|
Tal
Yossi
Orlev |
4 |
24-09-2010 |
Routine engine start for 10 min.
Assemble VOR antenna & camera on VS top
Empennage fairing.
Assemble the elevator trim servo
mechanism.
|
Yossi
Tal |
5 |
08-10-2010 |
Assemble Connectors for Navigation & Strobe tail light.
|
Yossi |
2.5 |
15-10-2010 |
Final assembling Taxi, Landing and Navigation Strobe lights.
|
Tal
Yossi |
2.5 |
22-10-2010 |
Assembly the Pittot kit.
Assembly the AOA Sport static probes in the outer bay of
the left wing.
Assembly connectors for the cabin flood lights.
|
Tal
Yossi |
4 |
05-11-2010 |
Assembly the Ailerons.
|
Tal
Yossi |
4 |
12-11-2010 |
Assembly the Empennage.
Balance the Elevators.
|
Tal
Yossi |
4 |
19-11-2010 |
Finish
Balance the Elevators.
Routine engine start for 10 min.
|
Tal
Yossi |
4 |
26-11-2010 |
Rivet the Dzus
fasteners on the top cowl
Assembly all antenna
|
Tal
Yossi |
4 |
14-12-2010 |
In process inspection by Shmuel Ozery...
This inspection is
specially
to get the OK to close all panels.
We present to Shmuel
the
documentation
we prepared for
inspection
|
Tal
Yossi |
4 |
17-12-2010
to
18-12-2010 |
Back to paint job, finishing the paint on
wheel
Fairings
and lower
engine cowl
|
Tal
Yossi |
8 |
06-02-2011
to
11-02-2011 |
Relocating the workshop to a new location, packing and preparing the new
workshop.
Working on the papers.
Routine engine start for 10 min.
|
Tal
Yossi |
4 |
26-02-2011 |
Unpacking and preparing the new
workshop.
Working on the papers.
In order to maneuver the plane inside the workshop we
made a wheel kit. now we can move the plane in any direction easily.
|
Tal
Yossi |
5 |
11-03-2011
to
17-03-2011 |
Working on all open issues going from back (Empennage) to front
(Engine). This is really a final push before moving to Airport for wing
attaching and first flight.
|
Tal
Yossi |
40 |
20-03-2011 |
Changed Oil and Filter.
Engine start for 30 min.
with closed cowls to monitor EGT and CHT.
|
Tal
Yossi |
4 |
21-03-2011 |
Temporary Wings attach as part of a special event for special guests
(confidential for now)
|
Tal
Yossi
Orlev |
4 |
25-03-2011
to
27-03-2011 |
Ailerons range check and adjust.
Update the AF-3400 software to 7-3-7-MV15
Update the Blue mountain software to
3.19p2
|
Yossi |
2 |
01-04-2011 |
Install the OAT sensors for the Blue Mountain and AF-3400 on the right
wing at the rear of the middle service plate.
|
Yossi
|
4 |
15-04-2011
to
25-04-2011 |
Working and finishing all uncompleted small task all around the
airplane. the major
task was
baffle seals and main and front wheel
fairings.
last two days after finishing all small tasks and installing every thing
in place we performed the most important and critical task. "weight
and balance" we borrowed
airplane scales (Calibrated by the Israeli "Office of Standards and
Regulation") and after measuring the main & nose wheel exact distance
from leading wing point (70 inc point from datum) we rolled up the
airplane on the scales balanced roll & pitch axis of the airplane and
weighted the
airplane according to the weigh
and balance table.
The exact results after calculation we will put at the POH which is
almost finished too.
Officially
we finished the work In the workshop.
Next is move to the airport
and
inspection.
|
Tal
Yossi |
80 |
26-04-2011
to
03-05-2011 |
Working on the papers, forms and POB.
Delivering all to the authority
and waiting for the results.
|
Tal
Yossi |
0 |
16-05-2011
to
18-05-2011 |
Today we moved the plane to the airport (Megiddo). The trip was OK and
we got a special welcome from the side wind which almost turned over the
plane from the track.
Attach the wings and prepare
the plane for the inspection.
|
Tal
Yossi
Orlev |
24 |
19-05-2011 |
Congratulation !!!!!!
Today we Passed the inspection.
|
Tal
Yossi
Orlev |
8 |
16-09-2010
to
19-05-2011 |
Total time till now |
Yossi
Tal
Orlev |
221 |
Congratulation !!!!!! |
|
First Flight &
Testing
Date
|
Task Description |
Done By |
Hours |
24-05-2011 |
Today we performed the first flight in Megiddo airport.
Very exciting
the plane behaved perfect.
Next we will carry out 40 hours of flight testing according to the plan.
|
Tal
Yossi
Orlev |
8 |
24-05-2011
to
24-05-2011 |
Total time till now |
Yossi
Tal
Orlev |
8 |
Congratulation !!!!!! |
|
Highlight and
special events
Date
|
Task Description |
Done By |
Hours |
01-02-2005 |
Visit to Van's Aircraft to see the RV-7 as an option to build. After
landing from the test flight with the RV-7 I saw the RV-9A in the hangar
and at that very moment I
decided that this is the ONE.
|
Tal |
0 |
01-05-2005 |
Ordered the Empennage and Wing kits
|
|
0 |
18-07-2005 |
The Empennage and Wing kits arrived. Box 4 has an outside minor damage. (
the parts inside are O.K)
serial number 91158.
Packing List
|
|
0 |
01-01-2005
To
01-12-2005 |
Converting the
warehouse into a
workshop.
1 - Electricity work, More lights, more outlets.
2 - Covering the inside walls and
ceiling with
plaster plates and thermal/acoustic
isolation plates between them and the
outside walls.
3 - Ordering and installing all the inside
furniture
needed for a workshop. (tables, shelf
etcetera)
4 - Ordering and installing all standard machinery (drilling machine,
clamp, strip saw, compressor etcetera)
|
|
0 |
01-12-2005
To
06-12-2005 |
1 - Unpacking and recognizing the special tools kit.
2 - Unpacking and recognizing the Empennage and Wing kit parts.
|
|
0 |
06-12-2005
Midnight |
Organization & Preparation Completed
|
|
0 |
01-09-2006 |
First construction inspection by Shmuel Ozery
certified aviation engineer and chief inspector of "Maintenance 2000"
|
|
0 |
19-11-2006 |
BIG shipment arrived today :
|
QB
fuselage
|
|
New
Lycoming
O-320 D2A
|
|
New
Sensenich
prop
|
|
Firewall forward kit
|
|
Finish
kit
|
|
Yossi
Tal
Oved
Sherman |
2.5 |
09-03-2007 |
Mr. Shmuel Ozeri (Maintenance 2000 LTD) came and examined the
project.....
LOOKS GOOD !!!!
|
|
0 |
23-04-2007 |
Orders during visit at "Sun 'n Fun"
Blue
Mountain:
(Main EIFS & Autopilot)
1-
EFIS Sport G4
2 -Digital Autopilot
Advanced
Flight Systems: (Engine monitoring Plus)
1 - AF-3400SP -
Sport System (Engine monitoring plus altitude, airspeed, VS)
2 - AF-4CYL - 4 Cylinder Sensor Pack
Visit at "Sun 'n Fan 2007"
see more details here
|
|
0 |
15-06-2007 |
In process inspection by Shmuel Ozery...
LOOKS GOOD !!!!
|
|
0 |
24-08-2007 |
In process inspection by Shmuel Ozery...
LOOKS GOOD !!!!
|
|
0 |
02-11-2007 |
Classic Aero Aviator Interior kit has arrived …. AMAZING WORK !!!!
|
|
0 |
05-07-2008 |
We had the honor to host the
monthly Israeli EAA meeting
in our workshop. During the evening,
members/builders exchanged views and information on techniques and
recent local events. We would like to thank all
participants and hope this
meeting
will become a stepping stone for future traditional meetings.
|
|
0 |
14-11-2008 |
In process inspection by Shmuel Ozery...
LOOKS GOOD !!!!
|
|
0 |
06-02-2009 |
In process inspection by Shmuel Ozery...
LOOKS GOOD !!!!
|
|
0 |
09-10-2009 |
First Engine Startup as
schedule.
Mr. Shmuel Ozeri (Maintenance 2000 LTD) examined the
entire project with a special focus on Engine.
We assembled the propeller adjusted the alternator belt and secured all
involved bolts for first startup.
Then we performed all necessary steps to
rinse the fuel system and build up the oil pressure (by hand)
At 14:16 we started the Engine for the first
time
WORKED
excellent
!!!!!
All EMS sensors read good readings, the idle needed a
little adjustment .
|
|
0 |
05-03-2010 |
In process inspection by Shmuel Ozery...
LOOKS GOOD !!!!
This inspection is
specially
to get the OK to close lower wing sheets.
we have to paint the aileron pushrods and rivet the rivets under the
tanks overlapping before closing the wings sheets.
|
|
0 |
14-12-2010 |
In process inspection by Shmuel Ozery...
LOOKS GOOD !!!!
This inspection is
specially
to get the OK to close all panels.
We present to Shmuel
the
documentation
we prepared for
inspection
|
|
0 |
19-05-2011 |
Congratulation !!!!!!
Today we Passed the inspection.
|
|
0 |
24-05-2011 |
Congratulation !!!!!!
Today we performed the firs flight.
|
Tal
Yossi
Orlev |
8 |
01-02-2005
to
24-05-2011 |
Total time |
Yossi
Tal
Orlev |
2.5 |
Congratulation !!!!!! |
|
|